ANALISIS PRODUKTIVITAS PEKERJA PADA PEKERJAAN DINDING DENGAN METODE TIME STUDY (STUDI KASUS : PROYEK PEMBANGUNAN GEDUNG TILC UNIVERSITAS GADJAH MADA) ANALYSIS OF WORKER PRODUCTIVITY IN WALL WORK WITH TIME STUDY METHOD (CASE STUDY: TILC BUILDING DEVELOPMENT PROJECT, GADJAH MADA UNIVERSITY)

Rediyatno, Apram and Dita Saputro, Cahyo (2021) ANALISIS PRODUKTIVITAS PEKERJA PADA PEKERJAAN DINDING DENGAN METODE TIME STUDY (STUDI KASUS : PROYEK PEMBANGUNAN GEDUNG TILC UNIVERSITAS GADJAH MADA) ANALYSIS OF WORKER PRODUCTIVITY IN WALL WORK WITH TIME STUDY METHOD (CASE STUDY: TILC BUILDING DEVELOPMENT PROJECT, GADJAH MADA UNIVERSITY). Tugas Akhir thesis, University Technology Yogyakarta.

[img]
Preview
Text
ABSTRAK_5140811117_Apram Rediyanto.pdf

Download (169kB) | Preview

Abstract

ABSTRAK Pembangunan yang saat ini terjadi di Indonesia meningkat pesat seiring dengan bertambahnya jumlah penduduk dan kemajuan teknologi sehingga mengakibatkan berkembangnya pembangunan infrastruktur di berbagai daerah, seperti Daerah Istimewa Yogyakarta. Salah satu pembangunan yang ada di Yogyakarta yaitu pembangunan gedung Teaching Industry Learning Center (TILC) Universitas Gadjah Mada. Produktivitas pekerja menjadi hal penting dalam sebuah proyek pembangunan. Oleh sebab itu, dibutuhkan adanya suatu evaluasi yang dapat menghitung secara ilmiah untuk mengukur produktivitas dengan rinci berdasarkan waktu kerja yang dilakukan oleh pekerja, sehingga diperlukan sebuah metode yang tepat untuk dapat menghitung produktivitas pekerja, khususnya pada pekerjaan dinding proyek pembangunan gedung TILC UGM. Metode yang tepat digunakan untuk menghitung produktivitas pekerja adalah metode time study melalui pencatatan waktu sehingga produktivitas pekerja dapat dihitung secara rinci. Dalam tugas akhir ini, analisis produktivitas pekerja dilakukan dengan menggunakan metode time study. Hasil analisis menunjukkan bahwa produktivitas pekerja pada pekerjaan dinding kelompok pekerja 1 lebih produktif dibanding kelompok pekerja 2 meskipun selisih nilai produktivitas kedua kelompok tidak jauh berbeda. Hal ini berarti bahwa kedua kelompok pekerja pada pekerjaan dinding dikatakan produktif. Nilai koefisien produktivitas di lapangan juga cenderung lebih rendah dibanding nilai koefisien berdasarkan AHSP SNI 2018. Kata kunci : Produktivitas, time study, pekerjaan dinding ABSTRACT The development that is currently taking place in Indonesia is increasing rapidly in line with the increasing population and technological advances which have resulted in the development of infrastructure development in various regions, such as the Yogyakarta Special Region. One of the developments in Yogyakarta is the construction of the Gadjah Mada University Teaching Industry Learning Center (TILC) building. Worker productivity is an important thing in a development project. Therefore, it is necessary to have an evaluation that can calculate scientifically to measure productivity in detail based on the work time done by workers, so that an appropriate method is needed to be able to calculate worker productivity, especially in the wall work of the UGM TILC building construction project. The appropriate method used to calculate worker productivity is the time study method through recording time so that worker productivity can be calculated in detail. In this final project, the analysis of worker productivity is carried out using the time study method. The results of the analysis show that the productivity of workers in the wall work of worker group 1 is more productive than worker group 2 even though the difference in productivity values between the two groups is not much different. This means that both groups of workers on wall work are said to be productive. The productivity coefficient value in the field also tends to be lower than the coefficient value based on AHSP SNI 2018. Keywords: Productivity, time study, wall work DAFTAR PUSTAKA Abubakar, Y., Wunas, S., Tjaronge, W., & Djamaluddin, R.(2017).Model Koefisien Produktivitas Pemasangan Bata Ringan pada Perumahan Sederhana.Prosiding Seminar Nasional Sains dan Teknologi (semnastek) UMJ 2017, 1 – 9. Ardi, F., Wanandy, K.C., & Alifen, R.S.(2015).Produktivitas Pekerja pada Pekerjaan Beton Bertulang pada Proyek Bangunan Bertingkat (Studi Kasus : Proyek Pembangunan Condominium Tp6).Jurnal Dimensi Pratama Teknik Sipil, 4(2). AHSP SNI 2018. Belladona, M., Antoro, E.D., & Sandra, A.(2019). Analisis Produktivitas Pekerja pada Pekerjaan Beton Bertulang Menggunakan Metode Time Study.Majalah teknik Simes, 13(1), 6 – 17. Dipohusodo, I.(1996).Manajemen Proyek dan Konstruksi Jilid II.Yogyakarta: Badan Penerbit Kanisius Ervianto, W.I.(2004).Teori Aplikasi Manajemen Proyek Konstruksi,Yogyakarta : Penerbit Andi. Ervianto, W.I.(2008).Pengukuran Produktivitas Pekerja Bnagunan dalam Proyek Konstruksi (Studi Kasus : Proyek Gedung Bertingkat di Surakarta).Jurnal Teknik Sipil, 9(1). Heap, Alan.(1987).Improving Site Productivity of the Construction Industry, Geneva : International Labour Organization. Natalia, M., Adibroto, F., & Lubis, R.(2020). Perbandingan Produktivitas Tenaga Kerja dengan Menggunakan Metode Time Study terhadap AHSP SNI 2018.Jurnal Teknik Sipil (SIKLUS), 6(2), 155 – 166. Puraro, E.R., Munasih & Iskandar, T.(2019). Analisis Perbandingan Koefisien Upah Kerja dan Bahan Pekerjaan Dinding Bata Ringan antara Aktualisasi dan SNI 2016.Student Journal Gelagar, 1(1), 15 – 23 Putra, M.O.P., Iriana, R.T., & Malik, A.(2019).Analisis Produktivitas Pekerjaan Struktur Beton Bertulang pada Proyek Gedung Polda Riau 2018.Jurnal Online Mahasiswa (JOM) FTEKNIK, 6, 1 – 13. Rully, T., & Rahmawati, N.T.(2015).Perencanaan Pengukuran Kerja dalam Menentukan Waktu Standar dengan Metode Time Study Guna Meningkatkan Produktivitas Kerja pada Divisi Pompa Minyak PT Bukaka Teknik Utama Tbk.Jurnal Ilmiah Manajemen Fakultas Ekonomi (JIMFE), 1(1), 12 – 18 Sudiarsa, M., Pratama, P.A.D.S., & Yasada, G.(2020).Analisis Produktivitas Pekerja pada Pekerjaan Dinding Wallplus Precast Ringan Proyek Perumahan Sekar Jepun Denpasar.Journal of Applied Civil Engineering and Infrastructure Technology (JACEIT), 1(2), 14 – 18. Syahrul, A.K.H.F.R., & Adistana, G.A.Y.P.(2018).Produktivitas Pekerja pada Pekerjaan Bata Ringan dengan Metode Time Study pada Bangunan Gedung Bertingkat di Surabaya.Jurnal Rekayasa Teknik Sipil,3(3). Trisiany, E.M., & Halim, E.(2006).Analisa Nilai Perbandingan Produktivitas Tenaga Kerja dengan Menggunakan Metode Standard dan Aktual (Studi Kasus Proyek X dan Y).Surabay

Item Type: Thesis (Skripsi, Tugas Akhir or Kerja Praktek) (Tugas Akhir)
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Divisions: Fakultas Sains dan Teknologi > S1 Teknik Sipil
Depositing User: Kaprodi S1 Teknik Sipil UTY
Date Deposited: 30 Dec 2021 08:34
Last Modified: 30 Dec 2021 08:34
URI: http://eprints.uty.ac.id/id/eprint/6780

Actions (login required)

View Item View Item