EARNED VALUE CONCEPT TERHADAP BIAYA DAN WAKTU MENGGUNAKAN METODE CRASHING SHIFT KERJA EARNED VALUE CONCEPT TO COST AND TIME USING THE WORKING SHIFT CRASHING METHOD

Pramata, Rama and Bhaskara, Adwitya (2020) EARNED VALUE CONCEPT TERHADAP BIAYA DAN WAKTU MENGGUNAKAN METODE CRASHING SHIFT KERJA EARNED VALUE CONCEPT TO COST AND TIME USING THE WORKING SHIFT CRASHING METHOD. Tugas Akhir thesis, University Technology Yogyakarta.

[img]
Preview
Text
5160811119_RAMA PRATAMA.pdf

Download (715kB) | Preview

Abstract

ABSTRAK Pembangunan workshop 3 madiun ini merupakan salah satu bangunan baru yang direncanakan terdiri dari 2 lantai dengan material penyusun utamanya baja. Bangunan yang direncanakan durasi sekitar 210 hari kalender dengan 8 jam kerja perhari. Bangunan mengalami keterlambatan di minggu 10 selama 20 hari setelah melakukan Earned Value Concept. Bangunan akan direncanakan menggunakan metode crashing shift kerja agar untuk meminimalisir durasi yang terlambat dan biaya lebih besar dari biaya sebelumnya. Penelitian kali ini akan merencanakan pada Workshop 3 kota Madiun menggunakan metode crashing shift kerja. Penelitian ini dimaksudkan untuk mendapatkan hasil perbandingan durasi dan biaya yang didapat dari penggunaan metode crashing shift kerja yang dianalisis dari data proyek. Metode penelitian bersifat deskriptif-analisis mengumpulkan data untuk perencanaan metode shift kerja dan membandingan waktu dan biaya pelaksanaan sebelum dan sesudah menggunakan metode crashing shift kerja. Data yang diambil menggunakan data sekunder yaitu data yang didapatkan melalui media perantara atau tidak dilakukan sendiri oleh peneliti. Data sekunder berupa laporan penyelidikan, penelitian sebelumnya, bukti yang telah ada dan juga dokumen-dokumen dari proyek tempat penelitian. Project acceleration dengan alternatif penambahan kerja shift pagi dan shift malam menunjukkan persentase durasi sebesar 28,10% atau 151 hari dan persentase biaya sebesar 1,47% lebih mahal dari total biaya sebelumnya. Rencana anggaran biaya normal untuk pelaksanaan 210 hari kalender adalah sebesar Rp. 19.416.533.660,29 sedangkan setelah di crashing biaya proyek menjadi sebesar Rp. 19.701.197.940,37. Kata kunci: crashing, earned value concept, metode shift, project acceleration Abstract The construction of the 3 Madiun workshop is one of the new buildings planned to consist of 2 floors with the main constituent material of steel. The planned building has a duration of about 210 calendar days with 8 hours of work per day. Buildings experience delays in week 10 for 20 days after performing the Earned Value Concept. The building was designed using the crashing work shift method in order to minimize late duration and the cost was greater than the previous cost. This research was carried out in Workshop 3 in Madiun city and used the work shift crashing method. This research was intended to obtain the results of the comparison of duration and cost obtained from the use of the work shift crashing method which was analyzed from the project data. The research method was descriptive analysis with data collected for planning the work shift method and compares the time and costs of implementation before and after using the work shift crashing method. Data taken using secondary data, namely data obtained through intermediary media or not done by the researcher himself. Secondary data were in the form of reports on investigations, previous research, existing evidence, and documents from the research site project. Project acceleration with the alternative addition of morning shift and night shift work showed a duration percentage of 28.10% or 151 days and a percentage of costs of 1.47% more expensive than the previous total cost. The normal budget plan for the execution of 210 calendar days was Rp. 19,416,533,660.29 while after the crashing the project cost was Rp. 19,701,197,940.37. Keywords: crashing, earned value concept, shift method, project acceleration

Item Type: Thesis (Skripsi, Tugas Akhir or Kerja Praktek) (Tugas Akhir)
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Divisions: Fakultas Sains dan Teknologi > S1 Teknik Sipil
Depositing User: Kaprodi S1 Teknik Sipil UTY
Date Deposited: 22 Oct 2020 01:30
Last Modified: 22 Oct 2020 01:30
URI: http://eprints.uty.ac.id/id/eprint/5981